Select a Different P6 Baseline

Select a different P6 baseline for a P6 schedule that already has a baseline assigned.

To select a different P6 baseline for a P6 schedule that already has a baseline assigned, complete the following steps:

  1. Select the S1 // Projects tab.
  2. Do one of the following:
    • In the Projects pane, right-click on the P6 project and select Change Baseline: <name of current baseline>.
    • Select the P6 project in the Projects pane then, in the Get External Data From group, click Oracle Primavera > Assign / Change Baseline.
  3. On the Open dialog box, select the P6 XER or XML that you want to set as the baseline project.
    After it is assigned, a black B () displays on the Primavera P6 file icon in the Projects panel of the workbook to show that it has an assigned baseline.
  4. Import the project data to import both the project and baseline files together.

Baselines can be reassigned, assigned, added, or deleted by right-clicking on the Primavera project.